Document
Document
  • Related documents Related
  • Full details Details
  • Report document? Report?
?

Use the data export button to extract customised data sets from the Ship Plan and Survey Report Collection. Available in TSV and CSV formats.

Date recorded as the time of writing.

Date of document

18/08/1915

The year in which a vessel’s construction is completed.

Year of ship completion

1902

The individual and/or organisation listed as having been responsible for constructing the vessel. This can/may be the same as the owner and/or manager.

Shipbuilder

Robert Stephenson & Co Ltd

The port or place in which the vessel’s construction took place, at the time of writing.

Place of build

Hebburn on Tyne

Unique internal numbers used for identifying, referring and retrieving a specific survey report.

Survey number

13668

Other/additional record(s) specifically mentioned, referenced or associated to another record.

Associated documents

Barry 14266

Records that constitute Lloyd’s Register’s first official encounters with a specific vessel, e.g. a survey report.

First entry?

N

The date of last visit by a surveyor.

Date of latest survey

16/08/1915

The individual and/or organisation listed that is responsible for the everyday management of a ship. This may be the same as the owner.

Ship manager

Daniolos Bros

Name of the individual/entity/organisation responsible for authoring the record

Document author

G C Vaux

Location where a vessel’s survey was undertaken.

Location of Survey

Swansea

Date of the meeting of the Classing Committee.

Date of Classing committee

09/11/1915

A vessel’s means of propulsion.

Propulsion

Steam

Is the steamer assisted by sail?

Sail assisted steamer

No

Location of construction for a vessel’s engines.

Location of engine build

Newcastle

Engine builder as written

North Eastern Marine Engineering Co

Is machinery fitted at the aft of the vessel?

Machinery aft?

No

Generally a smaller additional auxiliary boiler (often used while the vessel is at port).

Is a donkey boiler fitted?

No

Name of the Proving House responsible for the public testing and certification of a vessel’s anchors and/or chain cables.

Lloyd's Proving House?

No

Name of ship as recorded on the record

Ship name

Dimitrios

The process of transferring a vessel to water, but not necessarily her completion.

Launch Date

04/09/1902

Unique identifier for a given ship, it is assigned by a builder.

Yard no

72

Abbreviations of the names of ports with Lloyd’s Register survey offices.

Port of survey abbreviations

Sws

Official administrative title (often printed) of a record used by Lloyd’s Register or external organisations.

Document identity

9 Report of Survey for Repairs, &c., of Engines & Boilers

The port in which a vessel is registered or permanently based.

Port of registry

Andros

The date of first visit by a surveyor.

Date of first survey

26/07/1915

The individual and/or organisation listed

Ship owner

Daniolos Bros

An officially licensed mariner (post 1850) holding ultimate command and responsibility for a vessel.

Master

S Daniolos

Location where the document is written.

Location of Document Creation

Swansea

Classification symbol assigned to a vessel by Lloyd’s Register’s Classing Committee denoting the quality of construction and maintenance.

Classification

Deferred for No 3 &c

Broad categories and subdivisions of vessels related to their purpose or function.

Ship type

undefined

Predominant material(s) utilised in a vessel’s construction.

Material of construction

Steel

A ship’s total internal volume in ‘register tons’ (replaced by gross tonnage post 1982).

Gross Register Tonnage

2508

Date in which construction of a vessel’s engines were completed.

Year of engine build

1902

Confirmation as to whether the vessel was equipped with refrigeration machinery to aid in the transport of frozen or chilled cargo/goods.

Refrigeration machinery fitted for cargo purposes?

No

Does the vessel possess an auxiliary power source?

Auxillary

No

Is electric lighting fitted to the vessel?

Electric light fitted?

No

Physical extent of a record.

Number of parts

1

Report an issue with this document

Have you noticed missing or incorrect data or images for this document?
Please let us know and we will rectify the issue as soon as possible.