Use the data export button to extract customised data sets from the Ship Plan and Survey Report Collection. Available in TSV and CSV formats.
Date recorded as the time of writing.
21/02/1935
The year in which a vessel’s construction is completed.
1908
The individual and/or organisation listed as having been responsible for constructing the vessel. This can/may be the same as the owner and/or manager.
Richardson, Duck & Co
The port or place in which the vessel’s construction took place, at the time of writing.
Stockton
Unique internal numbers used for identifying, referring and retrieving a specific survey report.
3897
The port in which a vessel is registered or permanently based.
Chios
The date of first visit by a surveyor.
30/01/1935
The individual and/or organisation listed
Carras Bros
Location where the document is written.
Piraeus
Location where a vessel’s survey was undertaken.
Piraeus
Date of the meeting of the Classing Committee.
12/03/1935
The name of the port/place of destination given.
Black Sea
A vessel’s means of propulsion.
Steam
Is the steamer assisted by sail?
No
Location of construction for a vessel’s engines.
Stockton
Blair & Co Ltd
Is machinery fitted at the aft of the vessel?
No
Generally a smaller additional auxiliary boiler (often used while the vessel is at port).
No
Name of the Proving House responsible for the public testing and certification of a vessel’s anchors and/or chain cables.
No
The official record pronounced by the Committee
To be broken up
Recorded date for the vessel’s loss or disposal.
__/__/0000
Physical extent of a record.
1
Name of ship as recorded on the record
Fotini Carras
The process of transferring a vessel to water, but not necessarily her completion.
13/06/1908
Unique identifier for a given ship, it is assigned by a builder.
589
Abbreviations of the names of ports with Lloyd’s Register survey offices.
Pir
Official administrative title (often printed) of a record used by Lloyd’s Register or external organisations.
9 Report of Survey for Repairs, &c., of Engines & Boilers
Records that constitute Lloyd’s Register’s first official encounters with a specific vessel, e.g. a survey report.
N
The date of last visit by a surveyor.
06/02/1935
Name of the individual/entity/organisation responsible for authoring the record
Robert G Knox; William Rennie
Name of surveyor.
William Rennie
Classification symbol assigned to a vessel by Lloyd’s Register’s Classing Committee denoting the quality of construction and maintenance.
Deferred
Recorded information related to a vessel’s movements.
Piraeus; Black Sea
Broad categories and subdivisions of vessels related to their purpose or function.
undefined
Predominant material(s) utilised in a vessel’s construction.
Steel
A ship’s total internal volume in ‘register tons’ (replaced by gross tonnage post 1982).
4396
Date in which construction of a vessel’s engines were completed.
1908
Confirmation as to whether the vessel was equipped with refrigeration machinery to aid in the transport of frozen or chilled cargo/goods.
No
Does the vessel possess an auxiliary power source?
No
Is electric lighting fitted to the vessel?
No
A vessel’s calculated maximum speed.
1935
Contextual information related to the reasons of the vessel’s loss or disposal.
Laid up & resold for breaking up; May be sold again
1935
Have you noticed missing or incorrect data or images for this document?