Use the data export button to extract customised data sets from the Ship Plan and Survey Report Collection. Available in TSV and CSV formats.
Date recorded as the time of writing.
07/07/1909
The year in which a vessel’s construction is completed.
1909
The individual and/or organisation listed as having been responsible for constructing the vessel. This can/may be the same as the owner and/or manager.
Northumberland Shipbuilding Co Ltd
The port or place in which the vessel’s construction took place, at the time of writing.
Howden-on-Tyne
Unique internal numbers used for identifying, referring and retrieving a specific survey report.
56967
Additional numbers that feature on a given record that may be used for identification.
20363
Records that constitute Lloyd’s Register’s first official encounters with a specific vessel, e.g. a survey report.
N
Location where the document is written.
Newcastle
Classification symbol assigned to a vessel by Lloyd’s Register’s Classing Committee denoting the quality of construction and maintenance.
+100A1; (Contemplated)
A vessel’s means of propulsion.
Steam
Is the steamer assisted by sail?
No
Confirmation as to whether the vessel was equipped with refrigeration machinery to aid in the transport of frozen or chilled cargo/goods.
No
Does the vessel possess an auxiliary power source?
No
Is electric lighting fitted to the vessel?
No
A vessel’s calculated maximum speed.
1909
Physical extent of a record.
1
Name of ship as recorded on the record
Errington Court
The process of transferring a vessel to water, but not necessarily her completion.
19/06/1909
Unique identifier for a given ship, it is assigned by a builder.
162
Abbreviations of the names of ports with Lloyd’s Register survey offices.
Nwc
Official administrative title (often printed) of a record used by Lloyd’s Register or external organisations.
11b Surveys for Freeboard-Steam Ships
The port in which a vessel is registered or permanently based.
London
Name of the individual/entity/organisation responsible for authoring the record
A R Sneddon
Location where a vessel’s survey was undertaken.
Newcastle
Broad categories and subdivisions of vessels related to their purpose or function.
undefined
Predominant material(s) utilised in a vessel’s construction.
Steel
A ship’s total internal volume in ‘register tons’ (replaced by gross tonnage post 1982).
4224
Is machinery fitted at the aft of the vessel?
No
Generally a smaller additional auxiliary boiler (often used while the vessel is at port).
No
Name of the Proving House responsible for the public testing and certification of a vessel’s anchors and/or chain cables.
No
1909
Have you noticed missing or incorrect data or images for this document?