Use the data export button to extract customised data sets from the Ship Plan and Survey Report Collection. Available in TSV and CSV formats.
Name of ship as recorded on the record
Medway ( Plan of Arrangement for Strengthening in Engine & Boiler Space for Medway, 26th December 1885 1885, Profile Plan for Medway, 26th December 1885 1885, Half Midship Section Plan for Medway, 7th December 1885 1885, Plan of Main Boilers for Medway, 1885 1885, Steel Ship Report for Medway, 25th June 1886 1886, Report on Machinery for Medway, 30th June 1886 1886, Report of Survey for Repairs, &c for Medway, 28th September 1886 1886, Engine Forgings or Castings Form for Medway, 27th February 1886 1886, Tests of Boiler Steel for Medway, 27th January 1886 1886, Tests of Boiler Steel for Medway, 16th February 1886 1886, Tests of Boiler Steel for Medway, 20th February 1886 1886, Tests of Boiler Steel for Medway, 13th March 1886 1886, Tests of Boiler Steel for Medway, 27th March 1886 1886, Tests of Boiler Steel for Medway, 1st May 1886 1886, Plan of Arrangement of Pipes for Pumping Holds & Water Ballast Tanks for Medway, 28th April 1886 1886, Report of Survey for Repairs, &c for Medway, 13th January 1887 1887, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 3rd January 1887 1887, Report of Survey for Repairs, &c for Medway, 13th December 1887 1887, Report of Survey for Repais, &c, of Engines & Boilers for Medway, 14th December 1887 1887, Report of Survey for Repairs, &c for Medway, 11th September 1888 1888, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 13th September 1888 1888, Report of Survey for Repairs, &c for Medway, 30th May 1889 1889, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 28th May 1889 1889, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 12th October 1889 1889, Report of Survey for Repairs, &c for Medway, 18th June 1890 1890, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 20th June 1890 1890, Report of Survey for Repairs, &c for Medway, 23rd June 1891 1891, Report of Survey for Repairs, &c for Medway, 25th May 1892 1892, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 26th May 1892 1892, Report on Electric Lighting Installation for Medway, Undated no date, Dimensions of Spars for Medway, Undated no date )
The process of transferring a vessel to water, but not necessarily her completion.
20/05/1886 ( Plan of Arrangement for Strengthening in Engine & Boiler Space for Medway, 26th December 1885 1885, Profile Plan for Medway, 26th December 1885 1885, Half Midship Section Plan for Medway, 7th December 1885 1885, Plan of Main Boilers for Medway, 1885 1885, Steel Ship Report for Medway, 25th June 1886 1886, Report on Machinery for Medway, 30th June 1886 1886, Report of Survey for Repairs, &c for Medway, 28th September 1886 1886, Engine Forgings or Castings Form for Medway, 27th February 1886 1886, Tests of Boiler Steel for Medway, 27th January 1886 1886, Tests of Boiler Steel for Medway, 16th February 1886 1886, Tests of Boiler Steel for Medway, 20th February 1886 1886, Tests of Boiler Steel for Medway, 13th March 1886 1886, Tests of Boiler Steel for Medway, 27th March 1886 1886, Tests of Boiler Steel for Medway, 1st May 1886 1886, Plan of Arrangement of Pipes for Pumping Holds & Water Ballast Tanks for Medway, 28th April 1886 1886, Report of Survey for Repairs, &c for Medway, 13th January 1887 1887, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 3rd January 1887 1887, Report of Survey for Repairs, &c for Medway, 13th December 1887 1887, Report of Survey for Repais, &c, of Engines & Boilers for Medway, 14th December 1887 1887, Report of Survey for Repairs, &c for Medway, 11th September 1888 1888, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 13th September 1888 1888, Report of Survey for Repairs, &c for Medway, 30th May 1889 1889, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 28th May 1889 1889, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 12th October 1889 1889, Report of Survey for Repairs, &c for Medway, 18th June 1890 1890, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 20th June 1890 1890, Report of Survey for Repairs, &c for Medway, 23rd June 1891 1891, Report of Survey for Repairs, &c for Medway, 25th May 1892 1892, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 26th May 1892 1892, Report on Electric Lighting Installation for Medway, Undated no date, Dimensions of Spars for Medway, Undated no date )
Unique identifier for a given ship, it is assigned by a builder.
146 ( Plan of Arrangement for Strengthening in Engine & Boiler Space for Medway, 26th December 1885 1885, Profile Plan for Medway, 26th December 1885 1885, Half Midship Section Plan for Medway, 7th December 1885 1885, Plan of Main Boilers for Medway, 1885 1885, Steel Ship Report for Medway, 25th June 1886 1886, Report on Machinery for Medway, 30th June 1886 1886, Report of Survey for Repairs, &c for Medway, 28th September 1886 1886, Engine Forgings or Castings Form for Medway, 27th February 1886 1886, Tests of Boiler Steel for Medway, 27th January 1886 1886, Tests of Boiler Steel for Medway, 16th February 1886 1886, Tests of Boiler Steel for Medway, 20th February 1886 1886, Tests of Boiler Steel for Medway, 13th March 1886 1886, Tests of Boiler Steel for Medway, 27th March 1886 1886, Tests of Boiler Steel for Medway, 1st May 1886 1886, Plan of Arrangement of Pipes for Pumping Holds & Water Ballast Tanks for Medway, 28th April 1886 1886, Report of Survey for Repairs, &c for Medway, 13th January 1887 1887, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 3rd January 1887 1887, Report of Survey for Repairs, &c for Medway, 13th December 1887 1887, Report of Survey for Repais, &c, of Engines & Boilers for Medway, 14th December 1887 1887, Report of Survey for Repairs, &c for Medway, 11th September 1888 1888, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 13th September 1888 1888, Report of Survey for Repairs, &c for Medway, 30th May 1889 1889, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 28th May 1889 1889, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 12th October 1889 1889, Report of Survey for Repairs, &c for Medway, 18th June 1890 1890, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 20th June 1890 1890, Report of Survey for Repairs, &c for Medway, 23rd June 1891 1891, Report of Survey for Repairs, &c for Medway, 25th May 1892 1892, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 26th May 1892 1892, Report on Electric Lighting Installation for Medway, Undated no date, Dimensions of Spars for Medway, Undated no date )
Location where a vessel’s survey was undertaken.
Glasgow ( Plan of Arrangement for Strengthening in Engine & Boiler Space for Medway, 26th December 1885 1885, Profile Plan for Medway, 26th December 1885 1885, Half Midship Section Plan for Medway, 7th December 1885 1885, Plan of Main Boilers for Medway, 1885 1885, Steel Ship Report for Medway, 25th June 1886 1886, Report on Machinery for Medway, 30th June 1886 1886, Report of Survey for Repairs, &c for Medway, 28th September 1886 1886, Engine Forgings or Castings Form for Medway, 27th February 1886 1886, Tests of Boiler Steel for Medway, 27th January 1886 1886, Tests of Boiler Steel for Medway, 16th February 1886 1886, Tests of Boiler Steel for Medway, 20th February 1886 1886, Tests of Boiler Steel for Medway, 13th March 1886 1886, Tests of Boiler Steel for Medway, 27th March 1886 1886, Tests of Boiler Steel for Medway, 1st May 1886 1886, Plan of Arrangement of Pipes for Pumping Holds & Water Ballast Tanks for Medway, 28th April 1886 1886, Report of Survey for Repairs, &c for Medway, 13th January 1887 1887, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 3rd January 1887 1887, Report of Survey for Repairs, &c for Medway, 13th December 1887 1887, Report of Survey for Repais, &c, of Engines & Boilers for Medway, 14th December 1887 1887, Report of Survey for Repairs, &c for Medway, 11th September 1888 1888, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 13th September 1888 1888, Report of Survey for Repairs, &c for Medway, 30th May 1889 1889, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 28th May 1889 1889, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 12th October 1889 1889, Report of Survey for Repairs, &c for Medway, 18th June 1890 1890, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 20th June 1890 1890, Report of Survey for Repairs, &c for Medway, 23rd June 1891 1891, Report of Survey for Repairs, &c for Medway, 25th May 1892 1892, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 26th May 1892 1892, Report on Electric Lighting Installation for Medway, Undated no date )
A vessel’s means of propulsion.
Steam ( Plan of Arrangement for Strengthening in Engine & Boiler Space for Medway, 26th December 1885 1885, Profile Plan for Medway, 26th December 1885 1885, Half Midship Section Plan for Medway, 7th December 1885 1885, Plan of Main Boilers for Medway, 1885 1885, Steel Ship Report for Medway, 25th June 1886 1886, Report on Machinery for Medway, 30th June 1886 1886, Report of Survey for Repairs, &c for Medway, 28th September 1886 1886, Tests of Boiler Steel for Medway, 27th January 1886 1886, Tests of Boiler Steel for Medway, 16th February 1886 1886, Tests of Boiler Steel for Medway, 20th February 1886 1886, Tests of Boiler Steel for Medway, 13th March 1886 1886, Tests of Boiler Steel for Medway, 27th March 1886 1886, Tests of Boiler Steel for Medway, 1st May 1886 1886, Plan of Arrangement of Pipes for Pumping Holds & Water Ballast Tanks for Medway, 28th April 1886 1886, Report of Survey for Repairs, &c for Medway, 13th January 1887 1887, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 3rd January 1887 1887, Report of Survey for Repairs, &c for Medway, 13th December 1887 1887, Report of Survey for Repais, &c, of Engines & Boilers for Medway, 14th December 1887 1887, Report of Survey for Repairs, &c for Medway, 11th September 1888 1888, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 13th September 1888 1888, Report of Survey for Repairs, &c for Medway, 30th May 1889 1889, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 28th May 1889 1889, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 12th October 1889 1889, Report of Survey for Repairs, &c for Medway, 18th June 1890 1890, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 20th June 1890 1890, Report of Survey for Repairs, &c for Medway, 23rd June 1891 1891, Report of Survey for Repairs, &c for Medway, 25th May 1892 1892, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 26th May 1892 1892, Report on Electric Lighting Installation for Medway, Undated no date, Dimensions of Spars for Medway, Undated no date )
undefined ( Engine Forgings or Castings Form for Medway, 27th February 1886 1886 )
Is the steamer assisted by sail?
No ( Plan of Arrangement for Strengthening in Engine & Boiler Space for Medway, 26th December 1885 1885, Profile Plan for Medway, 26th December 1885 1885, Half Midship Section Plan for Medway, 7th December 1885 1885, Plan of Main Boilers for Medway, 1885 1885, Steel Ship Report for Medway, 25th June 1886 1886, Report on Machinery for Medway, 30th June 1886 1886, Report of Survey for Repairs, &c for Medway, 28th September 1886 1886, Engine Forgings or Castings Form for Medway, 27th February 1886 1886, Tests of Boiler Steel for Medway, 27th January 1886 1886, Tests of Boiler Steel for Medway, 16th February 1886 1886, Tests of Boiler Steel for Medway, 20th February 1886 1886, Tests of Boiler Steel for Medway, 13th March 1886 1886, Tests of Boiler Steel for Medway, 27th March 1886 1886, Tests of Boiler Steel for Medway, 1st May 1886 1886, Plan of Arrangement of Pipes for Pumping Holds & Water Ballast Tanks for Medway, 28th April 1886 1886, Report of Survey for Repairs, &c for Medway, 13th January 1887 1887, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 3rd January 1887 1887, Report of Survey for Repairs, &c for Medway, 13th December 1887 1887, Report of Survey for Repais, &c, of Engines & Boilers for Medway, 14th December 1887 1887, Report of Survey for Repairs, &c for Medway, 11th September 1888 1888, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 13th September 1888 1888, Report of Survey for Repairs, &c for Medway, 30th May 1889 1889, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 28th May 1889 1889, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 12th October 1889 1889, Report of Survey for Repairs, &c for Medway, 18th June 1890 1890, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 20th June 1890 1890, Report of Survey for Repairs, &c for Medway, 23rd June 1891 1891, Report of Survey for Repairs, &c for Medway, 25th May 1892 1892, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 26th May 1892 1892, Report on Electric Lighting Installation for Medway, Undated no date, Dimensions of Spars for Medway, Undated no date )
Is machinery fitted at the aft of the vessel?
No ( Plan of Arrangement for Strengthening in Engine & Boiler Space for Medway, 26th December 1885 1885, Profile Plan for Medway, 26th December 1885 1885, Half Midship Section Plan for Medway, 7th December 1885 1885, Plan of Main Boilers for Medway, 1885 1885, Steel Ship Report for Medway, 25th June 1886 1886, Report on Machinery for Medway, 30th June 1886 1886, Report of Survey for Repairs, &c for Medway, 28th September 1886 1886, Engine Forgings or Castings Form for Medway, 27th February 1886 1886, Tests of Boiler Steel for Medway, 27th January 1886 1886, Tests of Boiler Steel for Medway, 16th February 1886 1886, Tests of Boiler Steel for Medway, 20th February 1886 1886, Tests of Boiler Steel for Medway, 13th March 1886 1886, Tests of Boiler Steel for Medway, 27th March 1886 1886, Tests of Boiler Steel for Medway, 1st May 1886 1886, Plan of Arrangement of Pipes for Pumping Holds & Water Ballast Tanks for Medway, 28th April 1886 1886, Report of Survey for Repairs, &c for Medway, 13th January 1887 1887, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 3rd January 1887 1887, Report of Survey for Repairs, &c for Medway, 13th December 1887 1887, Report of Survey for Repais, &c, of Engines & Boilers for Medway, 14th December 1887 1887, Report of Survey for Repairs, &c for Medway, 11th September 1888 1888, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 13th September 1888 1888, Report of Survey for Repairs, &c for Medway, 30th May 1889 1889, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 28th May 1889 1889, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 12th October 1889 1889, Report of Survey for Repairs, &c for Medway, 18th June 1890 1890, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 20th June 1890 1890, Report of Survey for Repairs, &c for Medway, 23rd June 1891 1891, Report of Survey for Repairs, &c for Medway, 25th May 1892 1892, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 26th May 1892 1892, Report on Electric Lighting Installation for Medway, Undated no date, Dimensions of Spars for Medway, Undated no date )
Generally a smaller additional auxiliary boiler (often used while the vessel is at port).
No ( Plan of Arrangement for Strengthening in Engine & Boiler Space for Medway, 26th December 1885 1885, Profile Plan for Medway, 26th December 1885 1885, Half Midship Section Plan for Medway, 7th December 1885 1885, Plan of Main Boilers for Medway, 1885 1885, Steel Ship Report for Medway, 25th June 1886 1886, Report on Machinery for Medway, 30th June 1886 1886, Report of Survey for Repairs, &c for Medway, 28th September 1886 1886, Engine Forgings or Castings Form for Medway, 27th February 1886 1886, Tests of Boiler Steel for Medway, 27th January 1886 1886, Tests of Boiler Steel for Medway, 16th February 1886 1886, Tests of Boiler Steel for Medway, 20th February 1886 1886, Tests of Boiler Steel for Medway, 13th March 1886 1886, Tests of Boiler Steel for Medway, 27th March 1886 1886, Tests of Boiler Steel for Medway, 1st May 1886 1886, Plan of Arrangement of Pipes for Pumping Holds & Water Ballast Tanks for Medway, 28th April 1886 1886, Report of Survey for Repairs, &c for Medway, 13th January 1887 1887, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 3rd January 1887 1887, Report of Survey for Repairs, &c for Medway, 13th December 1887 1887, Report of Survey for Repais, &c, of Engines & Boilers for Medway, 14th December 1887 1887, Report of Survey for Repairs, &c for Medway, 11th September 1888 1888, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 13th September 1888 1888, Report of Survey for Repairs, &c for Medway, 30th May 1889 1889, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 28th May 1889 1889, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 12th October 1889 1889, Report of Survey for Repairs, &c for Medway, 18th June 1890 1890, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 20th June 1890 1890, Report of Survey for Repairs, &c for Medway, 23rd June 1891 1891, Report of Survey for Repairs, &c for Medway, 25th May 1892 1892, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 26th May 1892 1892, Report on Electric Lighting Installation for Medway, Undated no date, Dimensions of Spars for Medway, Undated no date )
Name of the Proving House responsible for the public testing and certification of a vessel’s anchors and/or chain cables.
No ( Plan of Arrangement for Strengthening in Engine & Boiler Space for Medway, 26th December 1885 1885, Profile Plan for Medway, 26th December 1885 1885, Half Midship Section Plan for Medway, 7th December 1885 1885, Plan of Main Boilers for Medway, 1885 1885, Steel Ship Report for Medway, 25th June 1886 1886, Report on Machinery for Medway, 30th June 1886 1886, Report of Survey for Repairs, &c for Medway, 28th September 1886 1886, Engine Forgings or Castings Form for Medway, 27th February 1886 1886, Tests of Boiler Steel for Medway, 27th January 1886 1886, Tests of Boiler Steel for Medway, 16th February 1886 1886, Tests of Boiler Steel for Medway, 20th February 1886 1886, Tests of Boiler Steel for Medway, 13th March 1886 1886, Tests of Boiler Steel for Medway, 27th March 1886 1886, Tests of Boiler Steel for Medway, 1st May 1886 1886, Plan of Arrangement of Pipes for Pumping Holds & Water Ballast Tanks for Medway, 28th April 1886 1886, Report of Survey for Repairs, &c for Medway, 13th January 1887 1887, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 3rd January 1887 1887, Report of Survey for Repairs, &c for Medway, 13th December 1887 1887, Report of Survey for Repais, &c, of Engines & Boilers for Medway, 14th December 1887 1887, Report of Survey for Repairs, &c for Medway, 11th September 1888 1888, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 13th September 1888 1888, Report of Survey for Repairs, &c for Medway, 30th May 1889 1889, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 28th May 1889 1889, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 12th October 1889 1889, Report of Survey for Repairs, &c for Medway, 18th June 1890 1890, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 20th June 1890 1890, Report of Survey for Repairs, &c for Medway, 23rd June 1891 1891, Report of Survey for Repairs, &c for Medway, 25th May 1892 1892, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 26th May 1892 1892, Report on Electric Lighting Installation for Medway, Undated no date, Dimensions of Spars for Medway, Undated no date )
The listed port to which a given vessel belongs.
Glasgow ( Steel Ship Report for Medway, 25th June 1886 1886, Report on Machinery for Medway, 30th June 1886 1886, Report of Survey for Repairs, &c for Medway, 28th September 1886 1886, Report of Survey for Repairs, &c for Medway, 13th January 1887 1887, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 3rd January 1887 1887, Report of Survey for Repairs, &c for Medway, 13th December 1887 1887, Report of Survey for Repais, &c, of Engines & Boilers for Medway, 14th December 1887 1887, Report of Survey for Repairs, &c for Medway, 11th September 1888 1888, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 13th September 1888 1888, Report of Survey for Repairs, &c for Medway, 30th May 1889 1889, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 28th May 1889 1889, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 12th October 1889 1889, Report of Survey for Repairs, &c for Medway, 18th June 1890 1890, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 20th June 1890 1890, Report of Survey for Repairs, &c for Medway, 23rd June 1891 1891, Report of Survey for Repairs, &c for Medway, 25th May 1892 1892, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 26th May 1892 1892 )
An officially licensed mariner (post 1850) holding ultimate command and responsibility for a vessel.
W Fry ( Steel Ship Report for Medway, 25th June 1886 1886, Report on Machinery for Medway, 30th June 1886 1886, Report of Survey for Repairs, &c for Medway, 28th September 1886 1886, Report of Survey for Repairs, &c for Medway, 13th January 1887 1887, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 13th September 1888 1888, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 12th October 1889 1889, Report of Survey for Repairs, &c for Medway, 18th June 1890 1890, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 20th June 1890 1890 )
William Foy ( Report of Survey for Repairs, &c for Medway, 13th December 1887 1887 )
Fry ( Report of Survey for Repairs, &c for Medway, 11th September 1888 1888 )
Foy ( Report of Survey for Repairs, &c for Medway, 30th May 1889 1889 )
Kennedy ( Report of Survey for Repairs, &c for Medway, 23rd June 1891 1891 )
A Kennedy ( Report of Survey for Repairs, &c for Medway, 25th May 1892 1892, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 26th May 1892 1892 )
Classification symbol assigned to a vessel by Lloyd’s Register’s Classing Committee denoting the quality of construction and maintenance.
+100A1; +LMC Steel; A & Cp ( Steel Ship Report for Medway, 25th June 1886 1886 )
+LMC ( Report on Machinery for Medway, 30th June 1886 1886 )
+100A1 ( Report of Survey for Repairs, &c for Medway, 28th September 1886 1886, Report of Survey for Repairs, &c for Medway, 13th January 1887 1887, Report of Survey for Repairs, &c for Medway, 13th December 1887 1887, Report of Survey for Repairs, &c for Medway, 11th September 1888 1888, Report of Survey for Repairs, &c for Medway, 30th May 1889 1889, Report of Survey for Repairs, &c for Medway, 23rd June 1891 1891 )
+100A1; +LMC ( Report of Survey for Repairs, &c of Engines & Boilers for Medway, 3rd January 1887 1887 )
100A1 1-87; LMC 6-86 ( Report of Survey for Repais, &c, of Engines & Boilers for Medway, 14th December 1887 1887 )
+100A1 12,87; +LMC 6,86 ( Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 13th September 1888 1888 )
+100A1; +LMC 6,86 ( Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 28th May 1889 1889 )
S S 10/89 ( Report of Survey for Repairs, &c of Engines & Boilers for Medway, 12th October 1889 1889 )
100A1; S S no 1-90; +LMC 6/90 ( Report of Survey for Repairs, &c for Medway, 18th June 1890 1890 )
+LMC 6/90 ( Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 20th June 1890 1890 )
Withdraw Class & Insert ... ( Report of Survey for Repairs, &c for Medway, 25th May 1892 1892 )
+100A1 6,91; S S Gl No 1-90; +LMC 6,90 ( Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 26th May 1892 1892 )
The name of the port/place of destination given.
Coasting ( Steel Ship Report for Medway, 25th June 1886 1886, Report of Survey for Repairs, &c for Medway, 28th September 1886 1886, Report of Survey for Repairs, &c for Medway, 13th January 1887 1887, Report of Survey for Repairs, &c for Medway, 11th September 1888 1888, Report of Survey for Repairs, &c for Medway, 30th May 1889 1889, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 12th October 1889 1889, Report of Survey for Repairs, &c for Medway, 18th June 1890 1890, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 20th June 1890 1890, Report of Survey for Repairs, &c for Medway, 23rd June 1891 1891, Report of Survey for Repairs, &c for Medway, 25th May 1892 1892, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 26th May 1892 1892 )
Bristol ( Report of Survey for Repairs, &c for Medway, 13th December 1887 1887 )
Location of construction for a vessel’s engines.
Glasgow ( Report on Machinery for Medway, 30th June 1886 1886, Engine Forgings or Castings Form for Medway, 27th February 1886 1886, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 20th June 1890 1890, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 26th May 1892 1892 )
J J Thomson ( Report of Survey for Repairs, &c of Engines & Boilers for Medway, 12th October 1889 1889 )
Type and configuration of the engine(s) supplied for a vessel.
Vertical Dynamo Compound Wound ( Report on Electric Lighting Installation for Medway, Undated no date )
The year in which a vessel’s construction is completed.
1886 ( Plan of Arrangement for Strengthening in Engine & Boiler Space for Medway, 26th December 1885 1885, Profile Plan for Medway, 26th December 1885 1885, Half Midship Section Plan for Medway, 7th December 1885 1885, Plan of Main Boilers for Medway, 1885 1885, Steel Ship Report for Medway, 25th June 1886 1886, Report on Machinery for Medway, 30th June 1886 1886, Report of Survey for Repairs, &c for Medway, 28th September 1886 1886, Engine Forgings or Castings Form for Medway, 27th February 1886 1886, Tests of Boiler Steel for Medway, 27th January 1886 1886, Tests of Boiler Steel for Medway, 16th February 1886 1886, Tests of Boiler Steel for Medway, 20th February 1886 1886, Tests of Boiler Steel for Medway, 13th March 1886 1886, Tests of Boiler Steel for Medway, 27th March 1886 1886, Tests of Boiler Steel for Medway, 1st May 1886 1886, Plan of Arrangement of Pipes for Pumping Holds & Water Ballast Tanks for Medway, 28th April 1886 1886, Report of Survey for Repairs, &c for Medway, 13th January 1887 1887, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 3rd January 1887 1887, Report of Survey for Repairs, &c for Medway, 13th December 1887 1887, Report of Survey for Repais, &c, of Engines & Boilers for Medway, 14th December 1887 1887, Report of Survey for Repairs, &c for Medway, 11th September 1888 1888, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 13th September 1888 1888, Report of Survey for Repairs, &c for Medway, 30th May 1889 1889, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 28th May 1889 1889, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 12th October 1889 1889, Report of Survey for Repairs, &c for Medway, 18th June 1890 1890, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 20th June 1890 1890, Report of Survey for Repairs, &c for Medway, 23rd June 1891 1891, Report of Survey for Repairs, &c for Medway, 25th May 1892 1892, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 26th May 1892 1892, Report on Electric Lighting Installation for Medway, Undated no date, Dimensions of Spars for Medway, Undated no date )
The individual and/or organisation listed as having been responsible for constructing the vessel. This can/may be the same as the owner and/or manager.
Charles Connell & Co ( Plan of Arrangement for Strengthening in Engine & Boiler Space for Medway, 26th December 1885 1885, Profile Plan for Medway, 26th December 1885 1885, Half Midship Section Plan for Medway, 7th December 1885 1885, Plan of Main Boilers for Medway, 1885 1885, Steel Ship Report for Medway, 25th June 1886 1886, Report on Machinery for Medway, 30th June 1886 1886, Report of Survey for Repairs, &c for Medway, 28th September 1886 1886, Engine Forgings or Castings Form for Medway, 27th February 1886 1886, Tests of Boiler Steel for Medway, 27th January 1886 1886, Tests of Boiler Steel for Medway, 16th February 1886 1886, Tests of Boiler Steel for Medway, 20th February 1886 1886, Tests of Boiler Steel for Medway, 13th March 1886 1886, Tests of Boiler Steel for Medway, 27th March 1886 1886, Tests of Boiler Steel for Medway, 1st May 1886 1886, Plan of Arrangement of Pipes for Pumping Holds & Water Ballast Tanks for Medway, 28th April 1886 1886, Report of Survey for Repairs, &c for Medway, 13th January 1887 1887, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 3rd January 1887 1887, Report of Survey for Repairs, &c for Medway, 13th December 1887 1887, Report of Survey for Repais, &c, of Engines & Boilers for Medway, 14th December 1887 1887, Report of Survey for Repairs, &c for Medway, 11th September 1888 1888, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 13th September 1888 1888, Report of Survey for Repairs, &c for Medway, 30th May 1889 1889, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 28th May 1889 1889, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 12th October 1889 1889, Report of Survey for Repairs, &c for Medway, 18th June 1890 1890, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 20th June 1890 1890, Report of Survey for Repairs, &c for Medway, 23rd June 1891 1891, Report of Survey for Repairs, &c for Medway, 25th May 1892 1892, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 26th May 1892 1892, Report on Electric Lighting Installation for Medway, Undated no date, Dimensions of Spars for Medway, Undated no date )
The port or place in which the vessel’s construction took place, at the time of writing.
Glasgow ( Plan of Arrangement for Strengthening in Engine & Boiler Space for Medway, 26th December 1885 1885, Profile Plan for Medway, 26th December 1885 1885, Half Midship Section Plan for Medway, 7th December 1885 1885, Plan of Main Boilers for Medway, 1885 1885, Steel Ship Report for Medway, 25th June 1886 1886, Report on Machinery for Medway, 30th June 1886 1886, Report of Survey for Repairs, &c for Medway, 28th September 1886 1886, Engine Forgings or Castings Form for Medway, 27th February 1886 1886, Tests of Boiler Steel for Medway, 27th January 1886 1886, Tests of Boiler Steel for Medway, 16th February 1886 1886, Tests of Boiler Steel for Medway, 20th February 1886 1886, Tests of Boiler Steel for Medway, 13th March 1886 1886, Tests of Boiler Steel for Medway, 27th March 1886 1886, Tests of Boiler Steel for Medway, 1st May 1886 1886, Plan of Arrangement of Pipes for Pumping Holds & Water Ballast Tanks for Medway, 28th April 1886 1886, Report of Survey for Repairs, &c for Medway, 13th January 1887 1887, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 3rd January 1887 1887, Report of Survey for Repairs, &c for Medway, 13th December 1887 1887, Report of Survey for Repais, &c, of Engines & Boilers for Medway, 14th December 1887 1887, Report of Survey for Repairs, &c for Medway, 11th September 1888 1888, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 13th September 1888 1888, Report of Survey for Repairs, &c for Medway, 30th May 1889 1889, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 28th May 1889 1889, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 12th October 1889 1889, Report of Survey for Repairs, &c for Medway, 18th June 1890 1890, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 20th June 1890 1890, Report of Survey for Repairs, &c for Medway, 23rd June 1891 1891, Report of Survey for Repairs, &c for Medway, 25th May 1892 1892, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 26th May 1892 1892, Report on Electric Lighting Installation for Medway, Undated no date, Dimensions of Spars for Medway, Undated no date )
Broad categories and subdivisions of vessels related to their purpose or function.
undefined ( Plan of Arrangement for Strengthening in Engine & Boiler Space for Medway, 26th December 1885 1885, Plan of Main Boilers for Medway, 1885 1885, Engine Forgings or Castings Form for Medway, 27th February 1886 1886, Tests of Boiler Steel for Medway, 27th January 1886 1886, Tests of Boiler Steel for Medway, 16th February 1886 1886, Tests of Boiler Steel for Medway, 20th February 1886 1886, Tests of Boiler Steel for Medway, 13th March 1886 1886, Tests of Boiler Steel for Medway, 27th March 1886 1886, Tests of Boiler Steel for Medway, 1st May 1886 1886 )
Screw Steamer ( Profile Plan for Medway, 26th December 1885 1885, Half Midship Section Plan for Medway, 7th December 1885 1885, Plan of Arrangement of Pipes for Pumping Holds & Water Ballast Tanks for Medway, 28th April 1886 1886, Dimensions of Spars for Medway, Undated no date )
Predominant material(s) utilised in a vessel’s construction.
Steel ( Plan of Arrangement for Strengthening in Engine & Boiler Space for Medway, 26th December 1885 1885, Profile Plan for Medway, 26th December 1885 1885, Half Midship Section Plan for Medway, 7th December 1885 1885, Plan of Main Boilers for Medway, 1885 1885, Steel Ship Report for Medway, 25th June 1886 1886, Report on Machinery for Medway, 30th June 1886 1886, Report of Survey for Repairs, &c for Medway, 28th September 1886 1886, Engine Forgings or Castings Form for Medway, 27th February 1886 1886, Tests of Boiler Steel for Medway, 27th January 1886 1886, Tests of Boiler Steel for Medway, 16th February 1886 1886, Tests of Boiler Steel for Medway, 20th February 1886 1886, Tests of Boiler Steel for Medway, 13th March 1886 1886, Tests of Boiler Steel for Medway, 27th March 1886 1886, Tests of Boiler Steel for Medway, 1st May 1886 1886, Plan of Arrangement of Pipes for Pumping Holds & Water Ballast Tanks for Medway, 28th April 1886 1886, Report of Survey for Repairs, &c for Medway, 13th January 1887 1887, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 3rd January 1887 1887, Report of Survey for Repairs, &c for Medway, 13th December 1887 1887, Report of Survey for Repais, &c, of Engines & Boilers for Medway, 14th December 1887 1887, Report of Survey for Repairs, &c for Medway, 11th September 1888 1888, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 13th September 1888 1888, Report of Survey for Repairs, &c for Medway, 30th May 1889 1889, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 28th May 1889 1889, Report of Survey for Repairs, &c for Medway, 18th June 1890 1890, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 20th June 1890 1890, Report of Survey for Repairs, &c for Medway, 23rd June 1891 1891, Report of Survey for Repairs, &c for Medway, 25th May 1892 1892, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 26th May 1892 1892, Report on Electric Lighting Installation for Medway, Undated no date, Dimensions of Spars for Medway, Undated no date )
Confirmation as to whether the vessel was equipped with refrigeration machinery to aid in the transport of frozen or chilled cargo/goods.
No ( Plan of Arrangement for Strengthening in Engine & Boiler Space for Medway, 26th December 1885 1885, Profile Plan for Medway, 26th December 1885 1885, Half Midship Section Plan for Medway, 7th December 1885 1885, Plan of Main Boilers for Medway, 1885 1885, Steel Ship Report for Medway, 25th June 1886 1886, Report on Machinery for Medway, 30th June 1886 1886, Report of Survey for Repairs, &c for Medway, 28th September 1886 1886, Engine Forgings or Castings Form for Medway, 27th February 1886 1886, Tests of Boiler Steel for Medway, 27th January 1886 1886, Tests of Boiler Steel for Medway, 16th February 1886 1886, Tests of Boiler Steel for Medway, 20th February 1886 1886, Tests of Boiler Steel for Medway, 13th March 1886 1886, Tests of Boiler Steel for Medway, 27th March 1886 1886, Tests of Boiler Steel for Medway, 1st May 1886 1886, Plan of Arrangement of Pipes for Pumping Holds & Water Ballast Tanks for Medway, 28th April 1886 1886, Report of Survey for Repairs, &c for Medway, 13th January 1887 1887, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 3rd January 1887 1887, Report of Survey for Repairs, &c for Medway, 13th December 1887 1887, Report of Survey for Repais, &c, of Engines & Boilers for Medway, 14th December 1887 1887, Report of Survey for Repairs, &c for Medway, 11th September 1888 1888, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 13th September 1888 1888, Report of Survey for Repairs, &c for Medway, 30th May 1889 1889, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 28th May 1889 1889, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 12th October 1889 1889, Report of Survey for Repairs, &c for Medway, 18th June 1890 1890, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 20th June 1890 1890, Report of Survey for Repairs, &c for Medway, 23rd June 1891 1891, Report of Survey for Repairs, &c for Medway, 25th May 1892 1892, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 26th May 1892 1892, Report on Electric Lighting Installation for Medway, Undated no date, Dimensions of Spars for Medway, Undated no date )
Does the vessel possess an auxiliary power source?
No ( Plan of Arrangement for Strengthening in Engine & Boiler Space for Medway, 26th December 1885 1885, Profile Plan for Medway, 26th December 1885 1885, Half Midship Section Plan for Medway, 7th December 1885 1885, Plan of Main Boilers for Medway, 1885 1885, Steel Ship Report for Medway, 25th June 1886 1886, Report on Machinery for Medway, 30th June 1886 1886, Report of Survey for Repairs, &c for Medway, 28th September 1886 1886, Engine Forgings or Castings Form for Medway, 27th February 1886 1886, Tests of Boiler Steel for Medway, 27th January 1886 1886, Tests of Boiler Steel for Medway, 16th February 1886 1886, Tests of Boiler Steel for Medway, 20th February 1886 1886, Tests of Boiler Steel for Medway, 13th March 1886 1886, Tests of Boiler Steel for Medway, 27th March 1886 1886, Tests of Boiler Steel for Medway, 1st May 1886 1886, Plan of Arrangement of Pipes for Pumping Holds & Water Ballast Tanks for Medway, 28th April 1886 1886, Report of Survey for Repairs, &c for Medway, 13th January 1887 1887, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 3rd January 1887 1887, Report of Survey for Repairs, &c for Medway, 13th December 1887 1887, Report of Survey for Repais, &c, of Engines & Boilers for Medway, 14th December 1887 1887, Report of Survey for Repairs, &c for Medway, 11th September 1888 1888, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 13th September 1888 1888, Report of Survey for Repairs, &c for Medway, 30th May 1889 1889, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 28th May 1889 1889, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 12th October 1889 1889, Report of Survey for Repairs, &c for Medway, 18th June 1890 1890, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 20th June 1890 1890, Report of Survey for Repairs, &c for Medway, 23rd June 1891 1891, Report of Survey for Repairs, &c for Medway, 25th May 1892 1892, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 26th May 1892 1892, Report on Electric Lighting Installation for Medway, Undated no date, Dimensions of Spars for Medway, Undated no date )
Is electric lighting fitted to the vessel?
No ( Plan of Arrangement for Strengthening in Engine & Boiler Space for Medway, 26th December 1885 1885, Profile Plan for Medway, 26th December 1885 1885, Half Midship Section Plan for Medway, 7th December 1885 1885, Plan of Main Boilers for Medway, 1885 1885, Steel Ship Report for Medway, 25th June 1886 1886, Report on Machinery for Medway, 30th June 1886 1886, Report of Survey for Repairs, &c for Medway, 28th September 1886 1886, Engine Forgings or Castings Form for Medway, 27th February 1886 1886, Tests of Boiler Steel for Medway, 27th January 1886 1886, Tests of Boiler Steel for Medway, 16th February 1886 1886, Tests of Boiler Steel for Medway, 20th February 1886 1886, Tests of Boiler Steel for Medway, 13th March 1886 1886, Tests of Boiler Steel for Medway, 27th March 1886 1886, Tests of Boiler Steel for Medway, 1st May 1886 1886, Plan of Arrangement of Pipes for Pumping Holds & Water Ballast Tanks for Medway, 28th April 1886 1886, Report of Survey for Repairs, &c for Medway, 13th January 1887 1887, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 3rd January 1887 1887, Report of Survey for Repairs, &c for Medway, 13th December 1887 1887, Report of Survey for Repais, &c, of Engines & Boilers for Medway, 14th December 1887 1887, Report of Survey for Repairs, &c for Medway, 11th September 1888 1888, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 13th September 1888 1888, Report of Survey for Repairs, &c for Medway, 30th May 1889 1889, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 28th May 1889 1889, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 12th October 1889 1889, Report of Survey for Repairs, &c for Medway, 18th June 1890 1890, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 20th June 1890 1890, Report of Survey for Repairs, &c for Medway, 23rd June 1891 1891, Report of Survey for Repairs, &c for Medway, 25th May 1892 1892, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 26th May 1892 1892, Report on Electric Lighting Installation for Medway, Undated no date, Dimensions of Spars for Medway, Undated no date )
Abbreviations of the names of ports with Lloyd’s Register survey offices.
Gls ( Steel Ship Report for Medway, 25th June 1886 1886, Report on Machinery for Medway, 30th June 1886 1886, Report of Survey for Repairs, &c for Medway, 28th September 1886 1886, Report of Survey for Repairs, &c for Medway, 13th January 1887 1887, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 3rd January 1887 1887, Report of Survey for Repairs, &c for Medway, 13th December 1887 1887, Report of Survey for Repais, &c, of Engines & Boilers for Medway, 14th December 1887 1887, Report of Survey for Repairs, &c for Medway, 11th September 1888 1888, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 13th September 1888 1888, Report of Survey for Repairs, &c for Medway, 30th May 1889 1889, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 28th May 1889 1889, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 12th October 1889 1889, Report of Survey for Repairs, &c for Medway, 23rd June 1891 1891, Report of Survey for Repairs, &c for Medway, 25th May 1892 1892, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 26th May 1892 1892, Report on Electric Lighting Installation for Medway, Undated no date )
Irn ( Report of Survey for Repairs, &c for Medway, 18th June 1890 1890, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 20th June 1890 1890 )
The individual and/or organisation listed
W Sloan & Co ( Steel Ship Report for Medway, 25th June 1886 1886, Report on Machinery for Medway, 30th June 1886 1886, Report of Survey for Repairs, &c for Medway, 28th September 1886 1886, Report of Survey for Repairs, &c for Medway, 13th January 1887 1887, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 3rd January 1887 1887, Report of Survey for Repairs, &c for Medway, 13th December 1887 1887, Report of Survey for Repais, &c, of Engines & Boilers for Medway, 14th December 1887 1887, Report of Survey for Repairs, &c for Medway, 30th May 1889 1889, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 28th May 1889 1889, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 12th October 1889 1889, Report of Survey for Repairs, &c for Medway, 18th June 1890 1890, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 20th June 1890 1890, Report of Survey for Repairs, &c for Medway, 23rd June 1891 1891, Report of Survey for Repairs, &c for Medway, 25th May 1892 1892, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 26th May 1892 1892 )
W Hoan & Co ( Report of Survey for Repairs, &c for Medway, 11th September 1888 1888, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 13th September 1888 1888 )
Name of surveyor.
Charles Fowling ( Steel Ship Report for Medway, 25th June 1886 1886, Report of Survey for Repairs, &c for Medway, 28th September 1886 1886, Report of Survey for Repairs, &c for Medway, 13th January 1887 1887 )
George Newcomb ( Engine Forgings or Castings Form for Medway, 27th February 1886 1886 )
Joseph Thomson ( Tests of Boiler Steel for Medway, 27th January 1886 1886, Tests of Boiler Steel for Medway, 16th February 1886 1886, Tests of Boiler Steel for Medway, 13th March 1886 1886 )
Charles Edwards ( Tests of Boiler Steel for Medway, 20th February 1886 1886, Tests of Boiler Steel for Medway, 27th March 1886 1886, Tests of Boiler Steel for Medway, 1st May 1886 1886 )
Walter E Robson ( Report of Survey for Repairs, &c of Engines & Boilers for Medway, 3rd January 1887 1887, Report of Survey for Repais, &c, of Engines & Boilers for Medway, 14th December 1887 1887 )
John Dawkins ( Report of Survey for Repairs, &c for Medway, 13th December 1887 1887, Report of Survey for Repairs, &c for Medway, 11th September 1888 1888, Report of Survey for Repairs, &c for Medway, 30th May 1889 1889 )
Charles Cooper ( Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 28th May 1889 1889 )
James Mollison; Richard J Beveridge ( Report of Survey for Repairs, &c of Engines & Boilers for Medway, 12th October 1889 1889 )
John Dawkins; Henry Hand ( Report of Survey for Repairs, &c for Medway, 18th June 1890 1890 )
John Sanderson ( Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 20th June 1890 1890, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 26th May 1892 1892 )
R Elliott ( Report of Survey for Repairs, &c for Medway, 23rd June 1891 1891, Report of Survey for Repairs, &c for Medway, 25th May 1892 1892 )
Recorded information related to a vessel’s movements.
Glasgow; Coasting ( Steel Ship Report for Medway, 25th June 1886 1886, Report of Survey for Repairs, &c for Medway, 28th September 1886 1886, Report of Survey for Repairs, &c for Medway, 13th January 1887 1887, Report of Survey for Repairs, &c for Medway, 11th September 1888 1888, Report of Survey for Repairs, &c for Medway, 30th May 1889 1889, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 12th October 1889 1889, Report of Survey for Repairs, &c for Medway, 18th June 1890 1890, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 20th June 1890 1890, Report of Survey for Repairs, &c for Medway, 23rd June 1891 1891, Report of Survey for Repairs, &c for Medway, 25th May 1892 1892, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 26th May 1892 1892 )
Glasgow; Bristol ( Report of Survey for Repairs, &c for Medway, 13th December 1887 1887 )
A ship’s total internal volume in ‘register tons’ (replaced by gross tonnage post 1982).
871 ( Steel Ship Report for Medway, 25th June 1886 1886, Report on Machinery for Medway, 30th June 1886 1886 )
870 ( Report of Survey for Repairs, &c for Medway, 28th September 1886 1886, Report of Survey for Repairs, &c for Medway, 13th January 1887 1887, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 3rd January 1887 1887, Report of Survey for Repairs, &c for Medway, 13th December 1887 1887, Report of Survey for Repais, &c, of Engines & Boilers for Medway, 14th December 1887 1887, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 13th September 1888 1888, Report of Survey for Repairs, &c for Medway, 30th May 1889 1889, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 28th May 1889 1889 )
475 ( Report of Survey for Repairs, &c for Medway, 11th September 1888 1888 )
831 ( Report of Survey for Repairs, &c of Engines & Boilers for Medway, 12th October 1889 1889, Report of Survey for Repairs, &c for Medway, 18th June 1890 1890, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 20th June 1890 1890, Report of Survey for Repairs, &c for Medway, 23rd June 1891 1891, Report of Survey for Repairs, &c for Medway, 25th May 1892 1892, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 26th May 1892 1892 )
Date in which construction of a vessel’s engines were completed.
1886 ( Report on Machinery for Medway, 30th June 1886 1886, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 3rd January 1887 1887, Report of Survey for Repais, &c, of Engines & Boilers for Medway, 14th December 1887 1887, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 13th September 1888 1888, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 28th May 1889 1889, Report of Survey for Repairs, &c of Engines & Boilers for Medway, 12th October 1889 1889, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 20th June 1890 1890, Report of Survey for Repairs, &c, of Engines & Boilers for Medway, 26th May 1892 1892 )
Have you noticed missing or incorrect data or images for this ship?
Please let us know and we will rectify the issue as soon as possible.