Use the data export button to extract customised data sets from the Ship Plan and Survey Report Collection. Available in TSV and CSV formats.
Date recorded as the time of writing.
04/01/1906
The year in which a vessel’s construction is completed.
1906
The individual and/or organisation listed as having been responsible for constructing the vessel. This can/may be the same as the owner and/or manager.
Robert Stephenson & Co
The port or place in which the vessel’s construction took place, at the time of writing.
Newcastle
Unique internal numbers used for identifying, referring and retrieving a specific survey report.
4304
Additional numbers that feature on a given record that may be used for identification.
Newcastle 49926
Records that constitute Lloyd’s Register’s first official encounters with a specific vessel, e.g. a survey report.
N
The date of last visit by a surveyor.
04/01/1906
An officially licensed mariner (post 1850) holding ultimate command and responsibility for a vessel.
George T Edwards
Location where the document is written.
Middlesbrough
Date of the meeting of the Classing Committee.
22/02/1907
Predominant material(s) utilised in a vessel’s construction.
Steel
A ship’s total internal volume in ‘register tons’ (replaced by gross tonnage post 1982).
3898
Date in which construction of a vessel’s engines were completed.
1906
Confirmation as to whether the vessel was equipped with refrigeration machinery to aid in the transport of frozen or chilled cargo/goods.
No
Does the vessel possess an auxiliary power source?
No
Is electric lighting fitted to the vessel?
No
Physical extent of a record.
1
Name of ship as recorded on the record
Dinsdalehall
The process of transferring a vessel to water, but not necessarily her completion.
22/11/1905
Unique identifier for a given ship, it is assigned by a builder.
92
Abbreviations of the names of ports with Lloyd’s Register survey offices.
Mdb
Official administrative title (often printed) of a record used by Lloyd’s Register or external organisations.
5 Report on Boilers
The listed port to which a given vessel belongs.
West Hartlepool
The date of first visit by a surveyor.
23/06/1906
The individual and/or organisation listed
Guthe Bros & Co
Name of the individual/entity/organisation responsible for authoring the record
R D Shilston; J T Findlay
Location where a vessel’s survey was undertaken.
Middlesbrough
A vessel’s means of propulsion.
Steam
Is the steamer assisted by sail?
No
Location of construction for a vessel’s engines.
Wallsend
North Eastern Marine Engineering Co Ltd
Is machinery fitted at the aft of the vessel?
No
Generally a smaller additional auxiliary boiler (often used while the vessel is at port).
No
Name of the Proving House responsible for the public testing and certification of a vessel’s anchors and/or chain cables.
No
Have you noticed missing or incorrect data or images for this document?
Please let us know and we will rectify the issue as soon as possible.