Use the data export button to extract customised data sets from the Ship Plan and Survey Report Collection. Available in TSV and CSV formats.
Date recorded as the time of writing.
13/01/1915
The year in which a vessel’s construction is completed.
1915
The individual and/or organisation listed as having been responsible for constructing the vessel. This can/may be the same as the owner and/or manager.
W Doxford & Sons Ltd
The port or place in which the vessel’s construction took place, at the time of writing.
Sunderland
The port in which a vessel is registered or permanently based.
Bideford
The individual and/or organisation listed
Instow Steamship Co Ltd
Location where the document is written.
Bideford
A vessel’s means of propulsion.
Steam
Is the steamer assisted by sail?
No
Type and configuration of the engine(s) supplied for a vessel.
Triple Expansion
Date in which construction of a vessel’s engines were completed.
1915
Confirmation as to whether the vessel was equipped with refrigeration machinery to aid in the transport of frozen or chilled cargo/goods.
No
Does the vessel possess an auxiliary power source?
No
Is electric lighting fitted to the vessel?
No
Physical extent of a record.
1
Name of ship as recorded on the record
Indian City
The process of transferring a vessel to water, but not necessarily her completion.
04/11/1914
Unique identifier for a given ship, it is assigned by a builder.
471
Official administrative title (often printed) of a record used by Lloyd’s Register or external organisations.
GR130 Vessels of 100 tons & upwards
Records that constitute Lloyd’s Register’s first official encounters with a specific vessel, e.g. a survey report.
N
The individual and/or organisation listed that is responsible for the everyday management of a ship. This may be the same as the owner.
William Reardon Smith
Physical arrangement of a ship’s masts, sails and rigging.
Sr - Schooner
Predominant material(s) utilised in a vessel’s construction.
Steel
A ship’s total internal volume in ‘register tons’ (replaced by gross tonnage post 1982).
4645
Location of construction for a vessel’s engines.
Sunderland
W Doxford & Sons Ltd
Is machinery fitted at the aft of the vessel?
No
Generally a smaller additional auxiliary boiler (often used while the vessel is at port).
No
Name of the Proving House responsible for the public testing and certification of a vessel’s anchors and/or chain cables.
No
Have you noticed missing or incorrect data or images for this document?
Please let us know and we will rectify the issue as soon as possible.