Use the data export button to extract customised data sets from the Ship Plan and Survey Report Collection. Available in TSV and CSV formats.
Date recorded as the time of writing.
17/09/1938
The year in which a vessel’s construction is completed.
1906
The individual and/or organisation listed as having been responsible for constructing the vessel. This can/may be the same as the owner and/or manager.
Workman, Clark & Co Ltd
The port or place in which the vessel’s construction took place, at the time of writing.
Belfast
Unique internal numbers used for identifying, referring and retrieving a specific survey report.
10417
The listed port to which a given vessel belongs.
Glasgow
The date of first visit by a surveyor.
16/09/1938
The individual and/or organisation listed
British India Steam Navigation Co
Location where the document is written.
Calcutta
Classification symbol assigned to a vessel by Lloyd’s Register’s Classing Committee denoting the quality of construction and maintenance.
Deferred
A vessel’s means of propulsion.
Steam
Is the steamer assisted by sail?
No
Location of construction for a vessel’s engines.
Belfast
Workman Clark & Co Ltd
Is machinery fitted at the aft of the vessel?
No
Generally a smaller additional auxiliary boiler (often used while the vessel is at port).
No
Name of the Proving House responsible for the public testing and certification of a vessel’s anchors and/or chain cables.
No
Contextual information related to the reasons of the vessel’s loss or disposal.
Sold for Breaking up
Physical extent of a record.
1
Name of ship as recorded on the record
Chyebassa
The process of transferring a vessel to water, but not necessarily her completion.
21/02/1907
Unique identifier for a given ship, it is assigned by a builder.
240
Abbreviations of the names of ports with Lloyd’s Register survey offices.
Cal
Official administrative title (often printed) of a record used by Lloyd’s Register or external organisations.
Report of Survey for Repairs, &c., of Engines & Boilers
Records that constitute Lloyd’s Register’s first official encounters with a specific vessel, e.g. a survey report.
N
The date of last visit by a surveyor.
16/09/1938
Name of the individual/entity/organisation responsible for authoring the record
B Peskett
Location where a vessel’s survey was undertaken.
Calcutta
Date of the meeting of the Classing Committee.
25/10/1938
Predominant material(s) utilised in a vessel’s construction.
Steel
A ship’s total internal volume in ‘register tons’ (replaced by gross tonnage post 1982).
6317
Date in which construction of a vessel’s engines were completed.
1905
Confirmation as to whether the vessel was equipped with refrigeration machinery to aid in the transport of frozen or chilled cargo/goods.
No
Does the vessel possess an auxiliary power source?
No
Is electric lighting fitted to the vessel?
No
The official record pronounced by the Committee
Broken up
Recorded date for the vessel’s loss or disposal.
__/__/0000
Have you noticed missing or incorrect data or images for this document?
Please let us know and we will rectify the issue as soon as possible.