Use the data export button to extract customised data sets from the Ship Plan and Survey Report Collection. Available in TSV and CSV formats.
Date recorded as the time of writing.
28/05/1920
The year in which a vessel’s construction is completed.
1916
The individual and/or organisation listed as having been responsible for constructing the vessel. This can/may be the same as the owner and/or manager.
William Dobson & Co
Previously referred to as signal letters (c.19th C), radio call signs enable a ship to communicate and are assigned by the International Telecommunications Union (ITU).
KFQS
The port in which a vessel is registered or permanently based.
London
The individual and/or organisation listed
The Hope Lighterage Co Ltd
Location where the document is written.
London
A vessel’s means of propulsion.
Motor (internal combustion)
Is the steamer assisted by sail?
No
Type and configuration of the engine(s) supplied for a vessel.
Internal Combustion Vertical
Date in which construction of a vessel’s engines were completed.
1915
Confirmation as to whether the vessel was equipped with refrigeration machinery to aid in the transport of frozen or chilled cargo/goods.
No
Does the vessel possess an auxiliary power source?
No
Is electric lighting fitted to the vessel?
No
A vessel’s calculated maximum speed.
1920
Physical extent of a record.
1
Name of ship as recorded on the record
Evelyn Hope
The process of transferring a vessel to water, but not necessarily her completion.
__/__/1916
The port or place in which the vessel’s construction took place, at the time of writing.
Newcastle
Official administrative title (often printed) of a record used by Lloyd’s Register or external organisations.
GR130 Vessels of 100 tons & upwards
Records that constitute Lloyd’s Register’s first official encounters with a specific vessel, e.g. a survey report.
N
The individual and/or organisation listed that is responsible for the everyday management of a ship. This may be the same as the owner.
Alan Robert Charles Johnston
Broad categories and subdivisions of vessels related to their purpose or function.
Barge
Predominant material(s) utilised in a vessel’s construction.
Steel
A ship’s total internal volume in ‘register tons’ (replaced by gross tonnage post 1982).
134
Location of construction for a vessel’s engines.
Stockholm
J & C G Bolinders
Is machinery fitted at the aft of the vessel?
No
Generally a smaller additional auxiliary boiler (often used while the vessel is at port).
No
Name of the Proving House responsible for the public testing and certification of a vessel’s anchors and/or chain cables.
No
1920
Have you noticed missing or incorrect data or images for this document?
Please let us know and we will rectify the issue as soon as possible.