Use the data export button to extract customised data sets from the Ship Plan and Survey Report Collection. Available in TSV and CSV formats.
Date recorded as the time of writing.
19/02/1919
The year in which a vessel’s construction is completed.
1919
The individual and/or organisation listed as having been responsible for constructing the vessel. This can/may be the same as the owner and/or manager.
The Ferro-Concrete Ship Construction Co Ltd
Unique identifier for a given ship, it is assigned by a builder.
99
Abbreviations of the names of ports with Lloyd’s Register survey offices.
Brw
Official administrative title (often printed) of a record used by Lloyd’s Register or external organisations.
Ferro-Concrete vessel
Records that constitute Lloyd’s Register’s first official encounters with a specific vessel, e.g. a survey report.
Y
The date of last visit by a surveyor.
07/02/1919
The individual and/or organisation listed that is responsible for the everyday management of a ship. This may be the same as the owner.
Leopold Walford Ltd
Name of the individual/entity/organisation responsible for authoring the record
Thomas S Shute; W E Hall
Location where a vessel’s survey was undertaken.
Barrow
Date of the meeting of the Classing Committee.
07/03/1919
The name of the port/place of destination given.
London; Londonderry
A vessel’s means of propulsion.
Steam
Is the steamer assisted by sail?
No
Confirmation as to whether the vessel was equipped with refrigeration machinery to aid in the transport of frozen or chilled cargo/goods.
No
Does the vessel possess an auxiliary power source?
No
Is electric lighting fitted to the vessel?
No
Physical extent of a record.
2
Name of ship as recorded on the record
Armistice
The process of transferring a vessel to water, but not necessarily her completion.
07/01/1919
Name of the shipbuilder as it appears on the record.
A Wiley for The Ferro Concrete Ship Construction Co Ltd
The port or place in which the vessel’s construction took place, at the time of writing.
Barrow in Furness
Unique internal numbers used for identifying, referring and retrieving a specific survey report.
1768
The listed port to which a given vessel belongs.
London
The date of first visit by a surveyor.
06/02/1918
The individual and/or organisation listed
Construction Co Ltd; The Ferro Concrete Ship Construction Co Ltd
An officially licensed mariner (post 1850) holding ultimate command and responsibility for a vessel.
T S Bowen
Location where the document is written.
Barrow
Classification symbol assigned to a vessel by Lloyd’s Register’s Classing Committee denoting the quality of construction and maintenance.
A1 for English Channel & Coasting Service; +LMC 2,19; Cargo batten not fitted; Lloyds A&C P
Recorded information related to a vessel’s movements.
Barrow; London; Londonderry
Physical arrangement of a ship’s masts, sails and rigging.
Sr - Schooner
Predominant material(s) utilised in a vessel’s construction.
Ferro-concrete
A ship’s total internal volume in ‘register tons’ (replaced by gross tonnage post 1982).
894
Is machinery fitted at the aft of the vessel?
No
Generally a smaller additional auxiliary boiler (often used while the vessel is at port).
No
Name of the Proving House responsible for the public testing and certification of a vessel’s anchors and/or chain cables.
No
Have you noticed missing or incorrect data or images for this document?
Please let us know and we will rectify the issue as soon as possible.