Document
Document
  • Related documents Related
  • Full details Details
  • Report document? Report?
?

Use the data export button to extract customised data sets from the Ship Plan and Survey Report Collection. Available in TSV and CSV formats.

Date recorded as the time of writing.

Date of document

30/05/1888

The year in which a vessel’s construction is completed.

Year of ship completion

1880

The individual and/or organisation listed as having been responsible for constructing the vessel. This can/may be the same as the owner and/or manager.

Shipbuilder

James Laing

The port or place in which the vessel’s construction took place, at the time of writing.

Place of build

Sunderland

Unique internal numbers used for identifying, referring and retrieving a specific survey report.

Survey number

48470

Other/additional record(s) specifically mentioned, referenced or associated to another record.

Associated documents

London 47401

The date of first visit by a surveyor.

Date of first survey

12/05/1888

The individual and/or organisation listed

Ship owner

West India & Panama Tel Co

Name of the individual/entity/organisation responsible for authoring the record

Document author

Thomas L Gray

Name of surveyor.

Surveyor

Thomas L Gray

Classification symbol assigned to a vessel by Lloyd’s Register’s Classing Committee denoting the quality of construction and maintenance.

Classification

+100A1; SS No 2-88

Recorded information related to a vessel’s movements.

Voyage information

London; St Thomas

Broad categories and subdivisions of vessels related to their purpose or function.

Ship type

undefined

Predominant material(s) utilised in a vessel’s construction.

Material of construction

Iron

A ship’s total internal volume in ‘register tons’ (replaced by gross tonnage post 1982).

Gross Register Tonnage

868

Is machinery fitted at the aft of the vessel?

Machinery aft?

No

Generally a smaller additional auxiliary boiler (often used while the vessel is at port).

Is a donkey boiler fitted?

No

Name of the Proving House responsible for the public testing and certification of a vessel’s anchors and/or chain cables.

Lloyd's Proving House?

No

Physical extent of a record.

Number of parts

1

Name of ship as recorded on the record

Ship name

Grappler

The process of transferring a vessel to water, but not necessarily her completion.

Launch Date

24/01/1880

Unique identifier for a given ship, it is assigned by a builder.

Yard no

254

Abbreviations of the names of ports with Lloyd’s Register survey offices.

Port of survey abbreviations

Lon

Official administrative title (often printed) of a record used by Lloyd’s Register or external organisations.

Document identity

Report of Survey for Repairs, &c.

Records that constitute Lloyd’s Register’s first official encounters with a specific vessel, e.g. a survey report.

First entry?

N

The date of last visit by a surveyor.

Date of latest survey

29/05/1888

An officially licensed mariner (post 1850) holding ultimate command and responsibility for a vessel.

Master

Farrier

Location where the document is written.

Location of Document Creation

London

Location where a vessel’s survey was undertaken.

Location of Survey

London

Date of the meeting of the Classing Committee.

Date of Classing committee

18/10/1889

The name of the port/place of destination given.

Destined voyage

St Thomas

A vessel’s means of propulsion.

Propulsion

Steam

Is the steamer assisted by sail?

Sail assisted steamer

No

Confirmation as to whether the vessel was equipped with refrigeration machinery to aid in the transport of frozen or chilled cargo/goods.

Refrigeration machinery fitted for cargo purposes?

No

Does the vessel possess an auxiliary power source?

Auxillary

No

Is electric lighting fitted to the vessel?

Electric light fitted?

No

Draft

1888

Report an issue with this document

Have you noticed missing or incorrect data or images for this document?
Please let us know and we will rectify the issue as soon as possible.