Use the data export button to extract customised data sets from the Ship Plan and Survey Report Collection. Available in TSV and CSV formats.
Date recorded as the time of writing.
24/09/1941
The year in which a vessel’s construction is completed.
1903
The individual and/or organisation listed as having been responsible for constructing the vessel. This can/may be the same as the owner and/or manager.
Sir Raylton Dixon & Co Ltd
The port or place in which the vessel’s construction took place, at the time of writing.
Middlesbrough
Other/additional record(s) specifically mentioned, referenced or associated to another record.
Newcastle 99754
Broad categories and subdivisions of vessels related to their purpose or function.
undefined
Predominant material(s) utilised in a vessel’s construction.
Steel
Confirmation as to whether the vessel was equipped with refrigeration machinery to aid in the transport of frozen or chilled cargo/goods.
No
Does the vessel possess an auxiliary power source?
No
Is electric lighting fitted to the vessel?
No
Physical extent of a record.
1
Name of ship as recorded on the record
Elna II
The process of transferring a vessel to water, but not necessarily her completion.
24/06/1903
Unique identifier for a given ship, it is assigned by a builder.
500
Official administrative title (often printed) of a record used by Lloyd’s Register or external organisations.
Memo
Records that constitute Lloyd’s Register’s first official encounters with a specific vessel, e.g. a survey report.
N
A vessel’s means of propulsion.
undefined
Is the steamer assisted by sail?
No
Is machinery fitted at the aft of the vessel?
No
Generally a smaller additional auxiliary boiler (often used while the vessel is at port).
No
Name of the Proving House responsible for the public testing and certification of a vessel’s anchors and/or chain cables.
No