Use the data export button to extract customised data sets from the Ship Plan and Survey Report Collection. Available in TSV and CSV formats.

Date recorded as the time of writing.

Date of document

07/03/1962

The year in which a vessel’s construction is completed.

Year of ship completion

1956

The individual and/or organisation listed as having been responsible for constructing the vessel. This can/may be the same as the owner and/or manager.

Shipbuilder

Cheoy Lee Shipyard

The port or place in which the vessel’s construction took place, at the time of writing.

Place of build

Hong Kong

Records that constitute Lloyd’s Register’s first official encounters with a specific vessel, e.g. a survey report.

First entry?

N

Location where the document is written.

Location of Document Creation

Pusan

A vessel’s means of propulsion.

Propulsion

Motor (internal combustion)

Is the steamer assisted by sail?

Sail assisted steamer

No

Confirmation as to whether the vessel was equipped with refrigeration machinery to aid in the transport of frozen or chilled cargo/goods.

Refrigeration machinery fitted for cargo purposes?

No

Does the vessel possess an auxiliary power source?

Auxillary

No

Is electric lighting fitted to the vessel?

Electric light fitted?

No

A vessel’s calculated maximum speed.

Speed (knots)

1962

Physical extent of a record.

Number of parts

1

Name of ship as recorded on the record

Ship name

Unryong

The process of transferring a vessel to water, but not necessarily her completion.

Launch Date

03/11/1956

Unique identifier for a given ship, it is assigned by a builder.

Yard no

652

Official administrative title (often printed) of a record used by Lloyd’s Register or external organisations.

Document identity

Certificate of Survey of Damage & Repair

Name of the individual/entity/organisation responsible for authoring the record

Document author

J Winn

Broad categories and subdivisions of vessels related to their purpose or function.

Ship type

undefined

Predominant material(s) utilised in a vessel’s construction.

Material of construction

Steel

A ship’s total internal volume in ‘register tons’ (replaced by gross tonnage post 1982).

Gross Register Tonnage

1049

Is machinery fitted at the aft of the vessel?

Machinery aft?

No

Generally a smaller additional auxiliary boiler (often used while the vessel is at port).

Is a donkey boiler fitted?

No

Name of the Proving House responsible for the public testing and certification of a vessel’s anchors and/or chain cables.

Lloyd's Proving House?

No

Draft

1962

Report an issue with this document

Have you noticed missing or incorrect data or images for this document?
Please let us know and we will rectify the issue as soon as possible.