Document
Document
  • Related documents Related
  • Full details Details
  • Report document? Report?
?

Use the data export button to extract customised data sets from the Ship Plan and Survey Report Collection. Available in TSV and CSV formats.

Date recorded as the time of writing.

Date of document

23/11/1910

The year in which a vessel’s construction is completed.

Year of ship completion

1910

The individual and/or organisation listed as having been responsible for constructing the vessel. This can/may be the same as the owner and/or manager.

Shipbuilder

Blyth Shipbuilding & Dry Docks Co Ltd

The port or place in which the vessel’s construction took place, at the time of writing.

Place of build

Blyth

Previously referred to as signal letters (c.19th C), radio call signs enable a ship to communicate and are assigned by the International Telecommunications Union (ITU).

Signal letter/Call sign

HRWP

The port in which a vessel is registered or permanently based.

Port of registry

Glasgow

The individual and/or organisation listed

Ship owner

The Syndic Steam Shipping Co

An officially licensed mariner (post 1850) holding ultimate command and responsibility for a vessel.

Master

Thomas Clark Jose

Broad categories and subdivisions of vessels related to their purpose or function.

Ship type

undefined

A vessel’s means of propulsion.

Propulsion

undefined

Is the steamer assisted by sail?

Sail assisted steamer

No

Type and configuration of the engine(s) supplied for a vessel.

Engine type

Triple Compound

Date in which construction of a vessel’s engines were completed.

Year of engine build

1910

Confirmation as to whether the vessel was equipped with refrigeration machinery to aid in the transport of frozen or chilled cargo/goods.

Refrigeration machinery fitted for cargo purposes?

No

Does the vessel possess an auxiliary power source?

Auxillary

No

Is electric lighting fitted to the vessel?

Electric light fitted?

No

Physical extent of a record.

Number of parts

1

Name of ship as recorded on the record

Ship name

Syndic

The process of transferring a vessel to water, but not necessarily her completion.

Launch Date

19/10/1910

Unique identifier for a given ship, it is assigned by a builder.

Yard no

156

A unique number allocated to a specific vessel by an official registration authority of the country of registry (flag) that the vessel belongs to (post. 1855).

Official number

129530

Official administrative title (often printed) of a record used by Lloyd’s Register or external organisations.

Document identity

GR130 Vessels of 100 tons & upwards

Records that constitute Lloyd’s Register’s first official encounters with a specific vessel, e.g. a survey report.

First entry?

N

The individual and/or organisation listed that is responsible for the everyday management of a ship. This may be the same as the owner.

Ship manager

Isaac B Pearson; Henry T Pearson

Location where the document is written.

Location of Document Creation

Glasgow

Physical arrangement of a ship’s masts, sails and rigging.

Rig

Sr - Schooner

Predominant material(s) utilised in a vessel’s construction.

Material of construction

Steel

A ship’s total internal volume in ‘register tons’ (replaced by gross tonnage post 1982).

Gross Register Tonnage

2727

Location of construction for a vessel’s engines.

Location of engine build

Wallsend

Engine builder as written

North Eastern Marine Engineering Co Ltd

Is machinery fitted at the aft of the vessel?

Machinery aft?

No

Generally a smaller additional auxiliary boiler (often used while the vessel is at port).

Is a donkey boiler fitted?

No

Name of the Proving House responsible for the public testing and certification of a vessel’s anchors and/or chain cables.

Lloyd's Proving House?

No

Report an issue with this document

Have you noticed missing or incorrect data or images for this document?
Please let us know and we will rectify the issue as soon as possible.