Use the data export button to extract customised data sets from the Ship Plan and Survey Report Collection. Available in TSV and CSV formats.
Date recorded as the time of writing.
30/12/1957
The year in which a vessel’s construction is completed.
1912
The individual and/or organisation listed as having been responsible for constructing the vessel. This can/may be the same as the owner and/or manager.
Lytham Ship & Engine Co Ltd
The port or place in which the vessel’s construction took place, at the time of writing.
Lytham
Unique internal numbers used for identifying, referring and retrieving a specific survey report.
148372
Other/additional record(s) specifically mentioned, referenced or associated to another record.
Liverpool 145917
Records that constitute Lloyd’s Register’s first official encounters with a specific vessel, e.g. a survey report.
N
The date of last visit by a surveyor.
24/12/1957
Name of the individual/entity/organisation responsible for authoring the record
R J Bann
Location where a vessel’s survey was undertaken.
Birkenhead
Date of the meeting of the Classing Committee.
14/01/1958
Predominant material(s) utilised in a vessel’s construction.
Steel
A ship’s total internal volume in ‘register tons’ (replaced by gross tonnage post 1982).
45
Date in which construction of a vessel’s engines were completed.
1912
Confirmation as to whether the vessel was equipped with refrigeration machinery to aid in the transport of frozen or chilled cargo/goods.
No
Does the vessel possess an auxiliary power source?
No
Is electric lighting fitted to the vessel?
No
The official record pronounced by the Committee
To be broken up
Physical extent of a record.
1
Name of ship as recorded on the record
Ullsgarth
The process of transferring a vessel to water, but not necessarily her completion.
13/07/1912
Unique identifier for a given ship, it is assigned by a builder.
454
Abbreviations of the names of ports with Lloyd’s Register survey offices.
Liv
Official administrative title (often printed) of a record used by Lloyd’s Register or external organisations.
9 Report of Periodical Surveys & Repairs of Machinery
The port in which a vessel is registered or permanently based.
Liverpool
The date of first visit by a surveyor.
23/12/1957
The individual and/or organisation listed
Rapid Coaling Syndicate Ltd
Location where the document is written.
Liverpool
Classification symbol assigned to a vessel by Lloyd’s Register’s Classing Committee denoting the quality of construction and maintenance.
MBS 12,57
A vessel’s means of propulsion.
Steam
Is the steamer assisted by sail?
No
Type and configuration of the engine(s) supplied for a vessel.
C 2 Cy
Lytham Shipbuilding & Engineering Co Ltd
Is machinery fitted at the aft of the vessel?
No
Generally a smaller additional auxiliary boiler (often used while the vessel is at port).
No
Name of the Proving House responsible for the public testing and certification of a vessel’s anchors and/or chain cables.
No
Contextual information related to the reasons of the vessel’s loss or disposal.
Sold for Breaking up
Have you noticed missing or incorrect data or images for this document?
Please let us know and we will rectify the issue as soon as possible.