Use the data export button to extract customised data sets from the Ship Plan and Survey Report Collection. Available in TSV and CSV formats.
Date recorded as the time of writing.
08/11/1933
The year in which a vessel’s construction is completed.
1892
The individual and/or organisation listed as having been responsible for constructing the vessel. This can/may be the same as the owner and/or manager.
William Dobson & Co
The port or place in which the vessel’s construction took place, at the time of writing.
Newcastle on Tyne
Records that constitute Lloyd’s Register’s first official encounters with a specific vessel, e.g. a survey report.
N
Broad categories and subdivisions of vessels related to their purpose or function.
undefined
Is the steamer assisted by sail?
No
A ship’s total internal capacity of a ship measured in register tons from the top of the floors to the tonnage deck.
966
Type and configuration of the engine(s) supplied for a vessel.
Triple Expansion 3 Cylinders
Confirmation as to whether the vessel was equipped with refrigeration machinery to aid in the transport of frozen or chilled cargo/goods.
No
Does the vessel possess an auxiliary power source?
No
Is electric lighting fitted to the vessel?
No
Used to indicate the capability of early reciprocating steam engines, based on dimensions rather than performance. It is not a true indication of actual engine power.
128
Also referred to as extreme breadth. The distance from the extreme starboard side to the extreme port side.
34.5
Physical extent of a record.
1
Name of ship as recorded on the record
Cabo Roca
The process of transferring a vessel to water, but not necessarily her completion.
16/11/1892
Unique identifier for a given ship, it is assigned by a builder.
56
Official administrative title (often printed) of a record used by Lloyd’s Register or external organisations.
Letter
Location where the document is written.
Seville
A vessel’s means of propulsion.
Steam
System of measurement that replaced ‘Builder’s Old Measurement’, taking a vessel’s internal capacity as the standard. Vessels built between 1836 and 1854 were legally required to display both tonnages.
1582
Tonnage derived by deducting from the gross register tonnage the capacity that in unavailable for cargo, e.g. machinery space, fuel, crew accommodation etc.
1136
North Eastern Marine Engineering Co Ltd
Is machinery fitted at the aft of the vessel?
No
Generally a smaller additional auxiliary boiler (often used while the vessel is at port).
No
Name of the Proving House responsible for the public testing and certification of a vessel’s anchors and/or chain cables.
No
Prescribed by flag/registration authorities, and usually excludes a small part of the stern. It is measured from the foreside of the stern at the extreme top to the afterside of the stern post.
235.4
Measurement from the underside of the upper deck on the centre line to the upper side of the bottom plating.
15.2
Have you noticed missing or incorrect data or images for this document?
Please let us know and we will rectify the issue as soon as possible.