Use the data export button to extract customised data sets from the Ship Plan and Survey Report Collection. Available in TSV and CSV formats.
Date recorded as the time of writing.
25/02/1907
The year in which a vessel’s construction is completed.
1903
The port or place in which the vessel’s construction took place, at the time of writing.
Gainsborough
Unique internal numbers used for identifying, referring and retrieving a specific survey report.
18780
Records that constitute Lloyd’s Register’s first official encounters with a specific vessel, e.g. a survey report.
Y
The date of last visit by a surveyor.
25/02/1907
Name of the individual/entity/organisation responsible for authoring the record
James Barclay
Name of surveyor.
James Barclay
Broad categories and subdivisions of vessels related to their purpose or function.
Tug
Predominant material(s) utilised in a vessel’s construction.
Steel
Type and configuration of the engine(s) supplied for a vessel.
Compound Surface condensing
Date in which construction of a vessel’s engines were completed.
1903
Confirmation as to whether the vessel was equipped with refrigeration machinery to aid in the transport of frozen or chilled cargo/goods.
No
Does the vessel possess an auxiliary power source?
No
Is electric lighting fitted to the vessel?
No
Physical extent of a record.
2
Name of ship as recorded on the record
Newark
The individual and/or organisation listed as having been responsible for constructing the vessel. This can/may be the same as the owner and/or manager.
J S Watson
Abbreviations of the names of ports with Lloyd’s Register survey offices.
Hul
Official administrative title (often printed) of a record used by Lloyd’s Register or external organisations.
4 Report on Machinery
The date of first visit by a surveyor.
25/02/1907
The individual and/or organisation listed
J S Watson
Location where the document is written.
Hull
Location where a vessel’s survey was undertaken.
Stainforth
A vessel’s means of propulsion.
undefined
Is the steamer assisted by sail?
No
Location of construction for a vessel’s engines.
Stockton
A Harker
Is machinery fitted at the aft of the vessel?
No
Generally a smaller additional auxiliary boiler (often used while the vessel is at port).
No
Name of the Proving House responsible for the public testing and certification of a vessel’s anchors and/or chain cables.
No