Use the data export button to extract customised data sets from the Ship Plan and Survey Report Collection. Available in TSV and CSV formats.
Date recorded as the time of writing.
14/03/1942
The year in which a vessel’s construction is completed.
1942
The individual and/or organisation listed as having been responsible for constructing the vessel. This can/may be the same as the owner and/or manager.
Bethlehem Steel Co
The port or place in which the vessel’s construction took place, at the time of writing.
Quincy, Massachusetts
Unique internal numbers used for identifying, referring and retrieving a specific survey report.
42277
The listed port to which a given vessel belongs.
Wilmington, De
The date of first visit by a surveyor.
02/02/1941
The individual and/or organisation listed
Sinclair Refining Co
Location where the document is written.
New York
Classification symbol assigned to a vessel by Lloyd’s Register’s Classing Committee denoting the quality of construction and maintenance.
2 WTB (sht) 500 lbs
Broad categories and subdivisions of vessels related to their purpose or function.
Tanker
Predominant material(s) utilised in a vessel’s construction.
Steel
A ship’s total internal volume in ‘register tons’ (replaced by gross tonnage post 1982).
10804
Date in which construction of a vessel’s engines were completed.
1941
Confirmation as to whether the vessel was equipped with refrigeration machinery to aid in the transport of frozen or chilled cargo/goods.
No
Does the vessel possess an auxiliary power source?
No
Is electric lighting fitted to the vessel?
No
A vessel’s calculated maximum speed.
1942
Physical extent of a record.
1
Name of ship as recorded on the record
Sheldon Clark
The process of transferring a vessel to water, but not necessarily her completion.
04/03/1942
Unique identifier for a given ship, it is assigned by a builder.
1493
Abbreviations of the names of ports with Lloyd’s Register survey offices.
N.Yk
Official administrative title (often printed) of a record used by Lloyd’s Register or external organisations.
5c Report on Water Tube Boilers
Records that constitute Lloyd’s Register’s first official encounters with a specific vessel, e.g. a survey report.
N
The date of last visit by a surveyor.
28/03/1942
Name of the individual/entity/organisation responsible for authoring the record
P W Wilson
Location where a vessel’s survey was undertaken.
Quincy
Date of the meeting of the Classing Committee.
08/04/1942
A vessel’s means of propulsion.
undefined
Is the steamer assisted by sail?
No
Location of construction for a vessel’s engines.
Trenton N J
De Laval Steam Turbine Co
Is machinery fitted at the aft of the vessel?
No
Generally a smaller additional auxiliary boiler (often used while the vessel is at port).
No
Name of the Proving House responsible for the public testing and certification of a vessel’s anchors and/or chain cables.
No
1942
Pertinent, useful or interesting recorded content.
Also refers to vessel Flagship Sinco
Have you noticed missing or incorrect data or images for this document?