Use the data export button to extract customised data sets from the Ship Plan and Survey Report Collection. Available in TSV and CSV formats.
Date recorded as the time of writing.
16/01/1954
The year in which a vessel’s construction is completed.
1945
The individual and/or organisation listed as having been responsible for constructing the vessel. This can/may be the same as the owner and/or manager.
Cook, Welton & Gemmell Ltd
The port or place in which the vessel’s construction took place, at the time of writing.
Beverley
Additional numbers that feature on a given record that may be used for identification.
44450
Records that constitute Lloyd’s Register’s first official encounters with a specific vessel, e.g. a survey report.
N
Name of the individual/entity/organisation responsible for authoring the record
I Barnicoat
Location where a vessel’s survey was undertaken.
Hull
Broad categories and subdivisions of vessels related to their purpose or function.
Trawler
Predominant material(s) utilised in a vessel’s construction.
Steel
A ship’s total internal volume in ‘register tons’ (replaced by gross tonnage post 1982).
361
Is machinery fitted at the aft of the vessel?
No
Generally a smaller additional auxiliary boiler (often used while the vessel is at port).
No
Name of the Proving House responsible for the public testing and certification of a vessel’s anchors and/or chain cables.
No
1954
Name of ship as recorded on the record
Bulby
The process of transferring a vessel to water, but not necessarily her completion.
08/10/1945
Unique identifier for a given ship, it is assigned by a builder.
756
Official administrative title (often printed) of a record used by Lloyd’s Register or external organisations.
C11 (Comp.) - Surveys for Freeboard
The port in which a vessel is registered or permanently based.
Fleetwood
The individual and/or organisation listed
National Trawling & Fishing Co Ltd
Location where the document is written.
Hull
Classification symbol assigned to a vessel by Lloyd’s Register’s Classing Committee denoting the quality of construction and maintenance.
+100A1; Steam Trawler
A vessel’s means of propulsion.
Steam
Is the steamer assisted by sail?
No
Confirmation as to whether the vessel was equipped with refrigeration machinery to aid in the transport of frozen or chilled cargo/goods.
No
Does the vessel possess an auxiliary power source?
No
Is electric lighting fitted to the vessel?
No
A vessel’s calculated maximum speed.
1954
Physical extent of a record.
1
Have you noticed missing or incorrect data or images for this document?
Please let us know and we will rectify the issue as soon as possible.