Use the data export button to extract customised data sets from the Ship Plan and Survey Report Collection. Available in TSV and CSV formats.
Date recorded as the time of writing.
__/02/1948
The year in which a vessel’s construction is completed.
1943
The individual and/or organisation listed as having been responsible for constructing the vessel. This can/may be the same as the owner and/or manager.
Bethlehem Fairfield Shipyard Inc
The port or place in which the vessel’s construction took place, at the time of writing.
Baltimore, Maryland
Unique internal numbers used for identifying, referring and retrieving a specific survey report.
7057
Additional numbers that feature on a given record that may be used for identification.
39466
The date of first visit by a surveyor.
__/01/1948
Name of the individual/entity/organisation responsible for authoring the record
Hamish C Murray
Location where a vessel’s survey was undertaken.
Liverpool
Predominant material(s) utilised in a vessel’s construction.
Steel
Confirmation as to whether the vessel was equipped with refrigeration machinery to aid in the transport of frozen or chilled cargo/goods.
No
Does the vessel possess an auxiliary power source?
No
Is electric lighting fitted to the vessel?
No
Physical extent of a record.
2
Name of ship as recorded on the record
Ivybank
The process of transferring a vessel to water, but not necessarily her completion.
__/__/1943
Unique identifier for a given ship, it is assigned by a builder.
2258
Abbreviations of the names of ports with Lloyd’s Register survey offices.
Liv
Official administrative title (often printed) of a record used by Lloyd’s Register or external organisations.
C11 Surveys for Freeboard - Conditions of Assignment
Records that constitute Lloyd’s Register’s first official encounters with a specific vessel, e.g. a survey report.
N
The date of last visit by a surveyor.
__/02/1948
Location where the document is written.
Liverpool
A vessel’s means of propulsion.
undefined
Is the steamer assisted by sail?
No
Is machinery fitted at the aft of the vessel?
No
Generally a smaller additional auxiliary boiler (often used while the vessel is at port).
No
Name of the Proving House responsible for the public testing and certification of a vessel’s anchors and/or chain cables.
No
Have you noticed missing or incorrect data or images for this document?
Please let us know and we will rectify the issue as soon as possible.