Use the data export button to extract customised data sets from the Ship Plan and Survey Report Collection. Available in TSV and CSV formats.
Date recorded as the time of writing.
31/05/1932
The year in which a vessel’s construction is completed.
1932
The individual and/or organisation listed as having been responsible for constructing the vessel. This can/may be the same as the owner and/or manager.
William Gray & Co Ltd
The port or place in which the vessel’s construction took place, at the time of writing.
West Hartlepool
Unique internal numbers used for identifying, referring and retrieving a specific survey report.
17157
The listed port to which a given vessel belongs.
Middlesbrough
The date of first visit by a surveyor.
11/01/1932
The individual and/or organisation listed
Tees Pilots Cutters Co Ltd
Location where the document is written.
Hartlepool
Classification symbol assigned to a vessel by Lloyd’s Register’s Classing Committee denoting the quality of construction and maintenance.
See FE Rpt
Broad categories and subdivisions of vessels related to their purpose or function.
Pilot
A vessel’s means of propulsion.
undefined
Is the steamer assisted by sail?
No
Location of construction for a vessel’s engines.
West Hartlepool
Central Marine Engine Works
Is machinery fitted at the aft of the vessel?
No
Generally a smaller additional auxiliary boiler (often used while the vessel is at port).
No
Name of the Proving House responsible for the public testing and certification of a vessel’s anchors and/or chain cables.
No
Contextual information related to the reasons of the vessel’s loss or disposal.
Sold to British Iron & Steel Corp for Breaking up
Name of ship as recorded on the record
B O Davies
The process of transferring a vessel to water, but not necessarily her completion.
23/04/1932
Unique identifier for a given ship, it is assigned by a builder.
1058
Abbreviations of the names of ports with Lloyd’s Register survey offices.
Hpl
Official administrative title (often printed) of a record used by Lloyd’s Register or external organisations.
5a Report on Boilers
Records that constitute Lloyd’s Register’s first official encounters with a specific vessel, e.g. a survey report.
N
The date of last visit by a surveyor.
30/05/1932
Name of the individual/entity/organisation responsible for authoring the record
R D Shilston
Location where a vessel’s survey was undertaken.
West Hartlepool
Date of the meeting of the Classing Committee.
14/06/1932
Physical arrangement of a ship’s masts, sails and rigging.
Cr - Cutter
Predominant material(s) utilised in a vessel’s construction.
Steel
A ship’s total internal volume in ‘register tons’ (replaced by gross tonnage post 1982).
173
Date in which construction of a vessel’s engines were completed.
1932
Confirmation as to whether the vessel was equipped with refrigeration machinery to aid in the transport of frozen or chilled cargo/goods.
No
Does the vessel possess an auxiliary power source?
No
Is electric lighting fitted to the vessel?
No
The official record pronounced by the Committee
To be broken up
Physical extent of a record.
1
Have you noticed missing or incorrect data or images for this document?
Please let us know and we will rectify the issue as soon as possible.