Use the data export button to extract customised data sets from the Ship Plan and Survey Report Collection. Available in TSV and CSV formats.
Date recorded as the time of writing.
16/12/1911
The year in which a vessel’s construction is completed.
1911
The individual and/or organisation listed as having been responsible for constructing the vessel. This can/may be the same as the owner and/or manager.
The Clyde Shipbuilding & Engineering Co Ltd
Unique identifier for a given ship, it is assigned by a builder.
296
Abbreviations of the names of ports with Lloyd’s Register survey offices.
Grk
Official administrative title (often printed) of a record used by Lloyd’s Register or external organisations.
Steel Steamer
Records that constitute Lloyd’s Register’s first official encounters with a specific vessel, e.g. a survey report.
Y
The date of last visit by a surveyor.
16/12/1911
An officially licensed mariner (post 1850) holding ultimate command and responsibility for a vessel.
Graham Charles Holloway
Location where the document is written.
Greenock
Location where a vessel’s survey was undertaken.
Port Glasgow
Date of the meeting of the Classing Committee.
27/12/1911
The name of the port/place of destination given.
Sydney
A vessel’s means of propulsion.
Steam
Is the steamer assisted by sail?
No
Confirmation as to whether the vessel was equipped with refrigeration machinery to aid in the transport of frozen or chilled cargo/goods.
No
Does the vessel possess an auxiliary power source?
No
Is electric lighting fitted to the vessel?
No
The official record pronounced by the Committee
To be broken up
Physical extent of a record.
2
Name of ship as recorded on the record
Montoro
The process of transferring a vessel to water, but not necessarily her completion.
24/10/1911
Name of the shipbuilder as it appears on the record.
Archibald Welch
The port or place in which the vessel’s construction took place, at the time of writing.
Port Glasgow
Unique internal numbers used for identifying, referring and retrieving a specific survey report.
16163
The listed port to which a given vessel belongs.
Sydney, N.S.W.
The date of first visit by a surveyor.
23/12/1910
The individual and/or organisation listed
Burns Philp & Co Ltd
Name of the individual/entity/organisation responsible for authoring the record
Edward John Tierney
Name of surveyor.
Edward John Tierney
Classification symbol assigned to a vessel by Lloyd’s Register’s Classing Committee denoting the quality of construction and maintenance.
+100A1 12,11; Lloyds A & CP; +LMC 12,11; FD
Recorded information related to a vessel’s movements.
Port Glasgow; Sydney
Physical arrangement of a ship’s masts, sails and rigging.
Sr - Schooner
Predominant material(s) utilised in a vessel’s construction.
Steel
A ship’s total internal volume in ‘register tons’ (replaced by gross tonnage post 1982).
4057
Is machinery fitted at the aft of the vessel?
No
Generally a smaller additional auxiliary boiler (often used while the vessel is at port).
No
Name of the Proving House responsible for the public testing and certification of a vessel’s anchors and/or chain cables.
No
Contextual information related to the reasons of the vessel’s loss or disposal.
Sold for Breaking up
Have you noticed missing or incorrect data or images for this document?
Please let us know and we will rectify the issue as soon as possible.